Office Move Checklist for Your First Construction Project

Office move checklist: a finished corner office with a wood desk, lounge seating, and large windows

With insight from Thomas Stocker, president of Stocker Associates

Someone at your company signed a lease or decided the current space needs a renovation, and the project landed on your desk. Maybe you’re the office manager or the practice administrator, and you’ve never run a construction project. This office move checklist is a jargon-free guide to the decisions to make early and the people to bring in, from lease signing to move-in day.

You’re in good company. Roughly 20 to 30 percent of Stocker Associates’ up-fit clients have someone leading a project for the first time. We’ve seen where those projects get stuck, and much of it happens on paper, before construction starts.

Start With a Needs List

The biggest gap for a first-timer is scope. We call it programming: how many offices and workstations you need, and whether the work calls for a workroom or production space. Without a clear needs list, no contractor can give you an accurate budget.

  1. Pull together a small group. Pair someone from IT with the person who runs the office, plus a representative from the team doing the company’s core work.
  2. Sort every item into need or nice to have. When a budget runs tight, nice-to-haves like a boardroom-style conference room are the first things to cut.
  3. Build the layout around what earns money. If the business runs on a large piece of equipment, plan the space around it first.
  4. Know your finish range. Think of it as a brand book for your contractor. A rough sense of how high-end the finishes should be keeps early numbers close to the final ones.
  5. Use what the existing space gives you. Our rule of thumb: if it covers about 75 percent of what you need, working with it usually costs far less than gutting it.

Bring In an Architect and a Contractor Before You Sign the Lease

An architect can run a test fit, a quick layout that shows whether your needs list fits the square footage. A contractor walking the building can spot costs the listing doesn’t show, like aging equipment that may become your responsibility once you sign. If your landlord is paying part of the build-out through a tenant improvement allowance, early pricing also shows whether that allowance will cover your plans.

Learn More: Tenant Improvement

Know Who Decides and What Matters Most

A project stalls when the person in the meetings can’t make decisions. We’ve seen teams need an answer this week while the one person who can give it is in Switzerland for the next three weeks. Before the project starts, figure out how decisions get made in your organization, and plan around when decision makers will be available.

We ask every client the same question early: what’s most important to you in this build-out? Some clients put schedule first, often to avoid holdover rent on their old space. Others have a fixed budget, or need a space that impresses high-end clients. Those priorities often compete, so knowing your answer up front shapes every option your contractor brings you.

Decisions to Lock in Early

On an ideal project, construction starts with every question answered and every material on order. These decisions cause the most trouble when they’re left as TBD:

  • Finishes and major materials. Settle these first, so everything can be ordered at the start with known lead times. These include but are not limited to flooring, lighting, electrical panels/transformers, HVAC units, generators, specialty doors, ceramic tile, steel packages, specialty glazing, operable partitions and other specialty finishes.
  • Furniture. Much office furniture is made overseas and shipped by boat. Order late, and you either push back move-in or settle for what’s available.
  • Outlet and infrastructure locations. “There’s no outlet for the copier” is a common late discovery. Adding power and data on paper costs far less than adding it after the walls close.
  • How the space gets used. Trace how people and paper move through it. In a medical office, follow a patient’s path from check-in to the exam room.
  • Internet service. If your company requires a specific provider, start right away. In some buildings, bringing in fiber takes up to six months.

How the Commercial Construction Process Runs

The commercial construction process for an office up-fit has two halves: the work on paper and the build itself. Most of your decisions, and most of the people you’ll bring in, belong to the first half.

  1. Test fit, before you sign the lease.
  2. Design, when you show plans to the staff who’ll use the space and bring in your furniture, teledata, and security vendors.
  3. Pricing and contract, after a final page-by-page review of the construction documents with your architect and general contractor.
  4. Permitting and construction, when you answer open questions by their due dates and walk the site at key points.

Bring vendors in late, and there’s only time to rush and take the low bid.

Watch how much of your timeline the paper half uses. Clients sometimes spend months on lease negotiation and design, then find a six-month build has four months left and ask, “Can’t you get it done in four months?” Scope drives schedule, and squeezing the build is where problems start.

Once construction starts, plan a site visit at wall rough-in, just before drywall goes up. Adding an outlet or connection you forgot costs far less now than after the drywall goes up.

Schedule a Consultation

Plan the Move Around the Finish Line

Leave one to two weeks between final inspection and move-in. On an average-size up-fit, if final inspections and the certificate of occupancy land on a Friday, plan the move for the following Friday. That week absorbs inspection issues and small fixes before they become a panic. Moving the next morning turns any small surprise into a missed move.

Negotiate a furniture-ready date separate from the completion date. Some jurisdictions want furniture in place for the final inspection, while others require a certificate of occupancy before it comes in, so ask your contractor early which rule applies. Two to three weeks before delivery, bring the furniture vendor onto the weekly project call.

Schedule the punch walk, the final check for defects and unfinished work, one to two weeks before the move, while the space is still empty. Lead the walk yourself; it’s your space.

Your Office Move Checklist

Print this office move checklist, or use it as the construction side of a larger office relocation checklist.

Before You Sign the Lease

  • Build a needs list with a small internal group, sorted into needs and nice-to-haves
  • Bring in an architect and a general contractor to evaluate the space and run a test fit
  • Find out what your tenant improvement allowance covers
  • Decide what matters most: schedule, cost, or quality

During Design

  • Name who can make decisions, and when they’re available
  • Lock in finishes and major materials
  • Choose a furniture vendor and order early
  • Bring in teledata, security, and IT vendors, and start fiber service right away if you need a specific provider
  • Show plans to the staff who’ll use the space
  • Review every page of the construction documents with your architect
  • Set a furniture-ready date and confirm local inspection rules

During Construction

  • Answer open questions by their due dates
  • Walk the site at wall rough-in

Before Move-In

  • Leave one to two weeks between final inspection and move-in
  • Walk the punch list while the space is empty

New to running a build-out? See how we work with first-time project leads.

Learn More: Who We Serve

Let’s Talk Before Your Move Date Is Set

Tell us about your space and your target date. If you have a floor plan of the new space or your current one, bring it. We’ll walk you through the process and flag the decisions to make first, so you know early whether the schedule fits.