DB7 Trucking Carrier Upfit


Subdivide Building for New Tenant

105 Cupped Oak Drive
Matthews, NC
15,000 SF

Date Completed: May 2021

Construction Scope Included:

  • Building a demising wall to divide an existing building into two suites to allow for new tenant

  • Constructing a new 1,450SF office with restrooms, show room, and manager’s office

  • Installing dock seals and edge of dock levelers at existing loading docks

  • Work was completed under accelerated schedule to accommodate the client lease required move dates